If the project duration is 18 months and the project manager is involved in the project for 50%, how shall we present the «# of units» and the «Unit value» in the budget?
If the employee is devoting certain percentage of time to the Action, then the duration shall be multiplied by the percentage of time of the staff will allocate to the Action e.g. 9 (18X50%) months would have been indicated under the column «# of Units» and in the «Unit Valueе» the full time (100%) salary shall be indicated.